December 5, 2025: Draft Business Plan for Community Farm Project Completed

Click to download theDraft Plan On December 5, Agnew::Beck Consulting submitted a draft Community Farm Business Plan to the City.  The draft included: Executive summary Project and farm overview Market analysis Community input notes / summary Financial narrative – including start up costs, operating expenses, and operating revenues Capital stack and fundraising strategy First year […]

November 30, 2025:  Equipment Building Completed

Bristol Prime Contractors completed the equipment building for the new Aalax Landfill in November, 2025. It has a man door and a garage door, cedar siding, and a metal roof.  They were also able to auger and prepare post holes for gate posts.  They will return in the spring of 2026 to install the fencing, […]