February 4, 2026 – Proposals were received from Alaska Geothermal, LLC; Awalix, LLC; Bristol Prime Contractors, LLC; and Drennon Construction and Consulting, Inc. All proposals were received via email prior to the deadline of 1:00 pm January 30, 2026.
Bids were publicly opened and read aloud via Zoom on February 3, 2026 at 1:00 pm.
| Vendor | Proposed Cost |
| Alaska Geothermal, LLC | $ 4,576,000 |
| Awalix, LLC | $ 3,756,160 |
| Bristol Prime Contractors, LLC | $ 5,052,069 |
| Drennon Construction & Consulting, Inc. | $ 5,872,000 |