Bulk Fuel Project Update – June 2, 2026
Bulk Fuel Project – The bulk fuel project is now in the construction phase. All of Prism’s material and supplies are on the island. Their crew will bring the small hand tools needed to do the work. Prism plans to be on the island on June 16th to begin construction. Prism will still be on track […]
Request for Proposals Published for preparing a Saint Paul Island Supplemental Safe Transportation Development Plan
The City of Saint Paul, Alaska has published a Request For Proposals for preparing a Saint Paul Island Supplemental Safe Transportation Development Plan to enhance the Action Plan completed in February 2025. Supplemental planning funding is needed to perform road safety audits, a road lighting plan and an assessment of critical transportation gaps in post-crash […]
Transformers enroute to SPI
Transformers, conduit, and other critical equipment and materials for completion of the Airport Distribution Feeder Replacement Project are enroute to Saint Paul Island and are expected to arrive in April or May. Contractors are expected to mobilize in May to complete the project.
Additional funding secured
The City was selected to receive additional grant funding from State of Alaska, Dept. of Commerce, Community and Economic Development, Div. of Community and Regional Affairs to complete the project, which experienced a cost overrun in 2025.
Alaska Geothermal selected as lowest bidder
On March 12, 2026, the City received three amended proposals before the deadline in response to Amendment 3 to RFP 25-03. The amended RFP requested breakdown of components of the project into a Base Bid and two Alternates. The lowest Base Bid was received from Alaska Geothermal, LLC. On March 13, 2026, the City issued […]
Construction to resume summer 2026
Bristol will be arriving to the island at the end of July to install the fencing and gate, the signage, and the bollards at the Aalax Landfill. 3 Tier Alaska will return in late summer to perform the final survey and prepare As-Builts.
Contract Executed With Kuna Engineering for Enhanced Drinking Water Resiliency Project
March 6, 2026 – The City received two proposals in response to RFP 25-02, for the Infrastructure Improvements to Enhance Drinking Water Resiliency project. This project is for the planning, design, procurement and installation of equipment and systems, and construction of three components which will improve the capabilities and capacity of the City of Saint Paul’s […]
Equipment and materials enroute to SPI; Construction scheduled for this summer
Contractors are in Seattle loading the barge with equipment and materials for the project. The barge is expected to arrive at SPI the first week of May. Contractors are developing their construction schedule to complete the project this summer.
Amended RFP Published For Saint Paul Small Boat Harbor Utilities Expansion Project
Bids were publicly opened on February 3, 2026, all of which exceeded the federal award from the Economic Development Administration (EDA). The City worked with Kuna Engineering to amend the RFP to be reposted. The amendment made no changes to the drawings or the scope of work. The amendment provides a base bid and […]
PRISM Design & Construction Procuring Materials for Bulk Fuel Project
PRISM Design and Construction have been working with the City and Electric Power Systems on procurement of supplies and materials for the project. PRISM has been sending submittals for review by the EPS engineers.