Site grading and road improvements were delayed at Aalax Landfill Project

April – June 2024:  Scheduled site grading and road improvements were delayed due to the ground remaining frozen through the second week of June, staff shortages, and an inoperable dump truck. Surveying and earthwork for the new landfill began in June. The surveyor was delayed one week arriving on Saint Paul Island due to weather […]