City Staff and Contractors Meeting With USDOT MARAD Staff For Harbor Improvements Planning Project
PND Engineering and the City have begun meeting with USDOT MARAD staff to begin the environmental review process for both this project and the City South Dock Renovations and New Berthing Dolphins Project. PND is planning to conduct a site visit sometime this fall.
Meetings and Site Visits begin on City South Dock Renovation Project
PND Engineering and the City have begun meeting with USDOT MARAD staff to begin the environmental review process for both this project and the Harbor Improvements Planning Project. PND is planning to conduct a site visit sometime this fall.
Electricians and Welders Mobilized to the Island to Work on Bulk Fuel Facility
PRISM contractors have been on island most of June and July. The Contractor’s electricians and welders mobilized to the island in late July. The two old fuel tanks have been demolished and disposed of. The two new fuel tanks were moved to the site. PRISM has set timbers and concrete pads for the new tanks. […]
Contractor Selected for Flood Mitigation Project
Four proposals in response to RFP 26-05 were received by the deadline of June 30, 2026. The City team reviewed and scored proposals. On July 17, the City issued a Notice of Intent to Award to Dowl. The City and Dowl are in contract negotiations.
Project Scope Revised to Meet Budget and Grant Deadlines
Alaska Geothermal and Kuna Engineering have been working to descope portions of the project to fit within the project budget and grant awards from EDA and Denali Commission. Unfortunately, due to significant inflation and a non-negotiable deadline to spend the grant funding received from EDA, the project will not include the sewer upgrades as originally […]
Alaska Geothermal placed the pumphouses on site
Alaska Geothermal placed the pumphouses on site in July for the Saint Paul Wastewater Lift Station Project.