ANNOUNCEMENTS & PROJECT UPDATES

Aalax Landfill Project: Project Status

January – March 2024: Remaining quotes for the building materials have been requested. Fencing and decals for vehicles were procured. Shipping of equipment and supplies is underway with a number of items scheduled for barge delivery in July including the dropboxes, track loader, excavator, and fencing. The water trailer has been received, inspected and put into commission. A contract with 3Tiers Alaska was executed for surveying. Design drawings for the equipment building were finalized and approved.
Facebook
X
LinkedIn
Email