Alaska Geothermal arrived on island to work on the wastewater lift station project. They are working with City Public Works staff reviewing drawings and asbuilts, performing locates of utilities, and moving the concrete and Conex boxes to the project site. Road work and trenching was conducted. B&B Electric assisted with power lines. Crews dug up and demolitioned the old wet well at the Ellerman site. Two new pump houses were placed at Ellerman and Sandy Lane. The linemen have placed a transformer at the Ellerman site.