EPA Prepares Environmental Assessment for New Aalax LandfillSite grading and road improvements were delayed at Aalax Landfill Project
Aalax Landfill Project: Project Status
Procurement of equipment and supplies begins for Aalax Landfill Project
Grant Source:
EPA through FY2022 Consolidated Appropriations Act Projects
Grant Amount:
$3,000,000
Timeline:
October 2023- September 2025
October 2023 –September 2024 Procurement of Equipment and Supplies | |
March – October 2024 Equipment and Supplies Shipped and Received | |
June-July 2025 Site Grading; Road Improvements; Install Fencing; Gate and Signage; and Equipment Building Foundation Work | |
August – September 2025 Erect Equipment Building and Burn Box | |
September 2025 Update Solid Waste Management Plan | |
September 2025 Grant Closeout |
For updates and involvement opportunities on this project and others, please check the project updates and announcements page.
For general information about the City of Saint Paul, please contact us at:
Phone: 907-546-3100
Fax: 1-866-570-9745
Email: info@stpaulak.com
PO Box 901
950 Gorbatch Street
Saint Paul, Alaska 99660