The Project will develop a new solid waste disposal facility on the 25-acre Aalax subdivision site in preparation for the closure of the existing Ataqan landfill in the spring of 2028. This project includes development of new landfill cells, fencing, signage, equipment building, access road and purchase of equipment for solid waste management including new burn boxes, heavy equipment, and drop boxes.
November 30, 2025: Equipment Building CompletedAalax Landfill Progress UpdateAalax Landfill Project: Project StatusHeavy Equipment & Materials for Landfill DeliveredAalax Landfill Project: Project StatusEPA Prepares Environmental Assessment for New Aalax LandfillSite grading and road improvements were delayed at Aalax Landfill ProjectAalax Landfill Progress UpdateProcurement of equipment and supplies begins for Aalax Landfill Project
Funding Source:
EPA through FY2022 Consolidated Appropriations Act Projects
Grant Amount:
$3,000,000
Timeline:
October 2023- September 2026
| October 2023 –September 2024 Procurement of Equipment and Supplies | |
| March – October 2024 Equipment and Supplies Shipped and Received | |
| June-August 2025 Site Grading, Road Improvements, and Equipment Building Foundation Work | |
| September-November 2025 Erect Equipment Building and Burn Box. | |
| Spring 2026 Install Fencing, Gate and Signage. Update Solid Waste Management Plan | |
| September 2026 Project Completed, Grant Closeout |
For updates and involvement opportunities on this project and others, please check the project updates and announcements page. Or, contact:
Jodi Plante,
Project Manager
Contracted Project Manager for the City of Saint Paul
Provided through Alaska Municipal Financial Solutions
jodi@akml.org
(907) 321-7663
For general information about the City of Saint Paul, please contact us at:
Phone: 907-546-3100
Fax: 1-866-570-9745
Email: info@stpaulak.com
PO Box 901
950 Gorbatch Street
Saint Paul, Alaska 99660