EPA Prepares Environmental Assessment for New Aalax LandfillSite grading and road improvements were delayed at Aalax Landfill Project
Aalax Landfill Project: Project Status
Procurement of equipment and supplies begins for Aalax Landfill Project
Grant Source:
EPA through FY2022 Consolidated Appropriations Act Projects
Grant Amount:
$3,000,000
Timeline:
October 2023- September 2025
October 2023 –September 2024 Procurement of Equipment and Supplies | |
March – October 2024 Equipment and Supplies Shipped and Received | |
June 2025 Site Grading | |
June 2025 Road Improvements | |
July 2025 Install Fencing, Gate and Signage | |
July 2025 Equipment Building Foundation Work | |
August – September 2025 Erect Equipment Building and Burn Box | |
September 2025 Update Solid Waste Management Plan | |
September 2025 Grant Closeout |
For general information about the City of Saint Paul, please contact us at:
Phone: 907-546-3100
Fax: 1-866-570-9745
Email: info@stpaulak.com
PO Box 901
950 Gorbatch Street
Saint Paul, Alaska 99660