Summary:

This project will develop a Saint Paul Island Supplemental Safe Transportation Development Plan to enhance the Pribilof Islands Transportation Safety Action Plan which was adopted in April 2025 (for more information on that Action Plan, visit https://projects.stpaulak.com/ss4a-action-plan/).

Supplemental planning will include road safety audits, a road lighting plan, and an assessment of critical transportation gaps in post-crash care. The issues addressed as part of a supplemental safe transportation development plan will help in developing transportation safety corridors and address the history of limited transportation and medical infrastructure concerns that have been a part of the history of the rural native community.

 

Project Milestones

 

 Spring 2026 : Publish Request for Proposals
 Summer 2026: Select Contractor, Execute Contract
 Fall 2026: Contractor Site Visit and Public Engagement
 Summer 2027: Draft Plan Submitted
 Fall 2027: Final Plan Submitted

Stay Informed

For updates and involvement opportunities on this project and others, please check the project updates and announcements page. Or, contact:

Jodi Plante,
Project Manager
Contracted Project Manager for the City of Saint Paul
Provided through Alaska Municipal Financial Solutions
jodi@akml.org
(907) 321-7663

Updates

RFP Published for preparing a Saint Paul Island Supplemental Safe Transportation Development Plan

Funding

Funding Source:

U.S. Department of Transportation, Federal Highway Administration, Office of Safety – $158,400

Project Costs:
$198,000

Timeline:
March 2026 – March 2028