Feedback from Public Meeting on Nov. 4, 2026

On November 4, 2026, Kuna Engineering held a Public Meeting on the project. Community members participated in discussions, shared their experiences, and provided feedback using dot stickers on maps to identify areas of concern and potential safety improvements. Download the results of the community meeting and the problem-spots map where participants placed the dot stickers. 

New Gas Station System Operational

The City of Saint Paul’s new Gas Station system is operational as of today. The Gas Station will now be open 24/7. The new point-of-sale system will not accept cash, only debit and credit cards will be accepted.  The point-of-sale system to activate the pumps is located inside the Gas Station building. Instructions on how […]

Public Workshop & Presentation: Road Lighting, Road Safety Audit & Post-Crash Care Plans

The City of Saint Paul received a USDOT grant award to complete a Supplemental to its FY22 Transportation Safety Action Plan. Kuna Engineering was selected as the firm to develop the supplemental plan which will including three primary components: a Road Lighting Plan, Road Safety Audit, and Post-Crash Care Plan. Kuna Engineering will be holding […]

Bulk Fuel Facility & Dispensing Tankage Project Nears Completion

The Bulk Fuel Facility and Dispensing Tankage project is nearly complete. From late September through October, crews worked on the welding the fuel piping, blowing out and testing the diesel piping, fixing leaks, backfilling the electrical trench, and installing doors on the pump box.  Crews plan to return the first week of November to complete […]

Wastewater Lift Stations Project Completed

The wastewater lift stations project, funded by Village Safe Water and EPA, was completed this month. This project completed the design and construction for the complete replacement of two existing lift stations at Ellerman Heights and Sandy Lane (also known as “Old Town”). The project included new concrete wet wells adjacent to a lift station […]

Aalax Landfill Project Continues

Fence installation continued through the month of October.  Signs were installed. Zender Environmental continues developing the Operations and Maintenance Manual for the new landfill. They are also producing a plan for the partial closure of the Ataqan Landfill. 3 Tiers Alaska will perform the final survey and prepare As-Builts when the site is finished.

Airport Feeder Update Sept. 29, 2026

The Airport Distribution Feeder replacement is scheduled to be completed by the end of 2026.  Crews will return to the island in October to restart the construction that had been put on hold while the City worked to obtain the last of the funding from USDA RUS.

DOWL and City Kick-Off Work on Flood Mitigation Project

The City and the selected firm, DOWL, kicked off the project in early September. DOWL is preparing for a site visit in October to visit the locations, collect data and hold a public involvement and outreach sessions.  

Bulk Fuel Facility Upgrade Project Moves Toward October Completion

Prism’s crew arrived on the island in June, and work began starting with the demolition and removal of the fencing, the existing fuel pumps and disconnecting the fuel and electrical lines. The welders arrived in July. Preparation for the new fuel tanks began mid-June and they were finished being installed on July 3rd along with […]

EPA Grants Officer Visits Aalax Landfill Site

The EPA Grants Officer made a site visit in August and was pleased with the work performed. He had no issues. The site work including grading has been finished. Contractors came on September 10th to install the gate and fencing, the bollards, and signs. Hydroseeding was applied on the exposed ground on the exterior of […]