Business Plan and Financial Feasibility Model Completed for Community Farm Planning Project
January 31, 2026 — Agnew::Beck Consulting submitted final planning and conceptual design documents for the Community Farm Business Plan to the City on January 31, 2026. These planning documents will be used to apply for funding to complete full design and construction. Click here to read the Business Plan.
12/8/25 City publishes RFP for construction
On December 8, 2025 the City published the Request for Proposals 25-03 seeking bids for the construction phase of the project, including demolition of the existing lift station and construction of a new lift station. To be considered, proposals must be received via email no later than January 16, 2026 no later than 2:00 pm […]
December 5, 2025: Draft Business Plan for Community Farm Project Completed
Click to download theDraft Plan On December 5, Agnew::Beck Consulting submitted a draft Community Farm Business Plan to the City. The draft included: Executive summary Project and farm overview Market analysis Community input notes / summary Financial narrative – including start up costs, operating expenses, and operating revenues Capital stack and fundraising strategy First year […]
December 8, 2025: Pump House Buildings Under Construction
Alaska Geothermal is currently constructing the pump house buildings in their Fairbanks shop. Once they are constructed, AGT will install electrical and mechanical components.
November 30, 2025: Equipment Building Completed
Bristol Prime Contractors completed the equipment building for the new Aalax Landfill in November, 2025. It has a man door and a garage door, cedar siding, and a metal roof. They were also able to auger and prepare post holes for gate posts. They will return in the spring of 2026 to install the fencing, […]
City Reviewing Proposals for Enhance Drinking Water System Resilience Project
December 10, 2025: The City received 2 proposals in response to the RFP for this project. One from Kuna Engineering and the other from Bristol Prime Contractors. Both were received via email prior to the deadline of 5:00 pm December 10, 2025. The City is in the process of reviewing the proposals and calling references. […]
Proposal Deadline Extended for Enhance Drinking Water System Resilience Project
December 1, 2025: The City has received numerous questions to this RFP. Answers to all questions and additional supporting documents for the project have been posted on the RFP page https://stpaulak.com/rfp-no-25-02/ . The City has extended the deadline for proposals to December 10, 2025.
Airport Feeder Update/Announcement October 30, 2025
Joe Kozloff performing utility locates for the EPC lineman crew. Electrical transformers for the project started arriving on Coastal Transportation in October 2025. The City Public Works staff will pick them up and store them until work resumes in the spring of 2026. The electrical switch is expected to arrive in Spring of 2026. Electric […]
Contractors constructing equipment building for the new Aalax Landfill.
Bristol Prime Contractors have been on site since early September erecting the equipment building for the new Aalax Landfill. City Public Works staff and TDX staff have been assisting with the project. The building should be completed by mid-November. City Public Works staff will next be leveling out the ground for the fence line to […]
Agnew::Beck Consultants Developing Draft Business Plan for Community Farm
October 2025 —The Agnew::Beck team is currently working on developing the draft business plan. Specifically, they are: Developing the financial model that will feed into the financial pro forma and feasibility picture. The financial model and pro forma will take into consideration the estimated capital and operations and maintenance costs. Funding sources and strategies overview […]