Project Updates
Airport Feeder Update/Announcement October 30, 2025
Joe Kozloff performing utility locates for the EPC lineman crew. Electrical transformers for the project started arriving on Coastal Transportation in October 2025. The City
PRISM Design & Construction Procuring Materials for Bulk Fuel Project
PRISM Design and Construction have been working with the City and Electric Power Systems on procurement of supplies and materials for the project. PRISM has
Contractors constructing equipment building for the new Aalax Landfill.
Bristol Prime Contractors have been on site since early September erecting the equipment building for the new Aalax Landfill. City Public Works staff and TDX
Agnew::Beck Consultants Developing Draft Business Plan for Community Farm
October 2025 —The Agnew::Beck team is currently working on developing the draft business plan. Specifically, they are: Developing the financial model that will feed into
City of Saint Paul awarded $4.6 million EPA grant to improve drinking water resilience
The City of Saint Paul was selected as a recipient of a $4,651,170 grant from the U.S. Environmental Protection Agency (EPA) to support drinking water systems in underserved, small, and disadvantaged communities while reducing impacts of climate change.
Aalax Landfill Progress Update
City Public Works staff are currently working on site to move the sand dune hill in order to level out the ground to create a
New electric line is now live, feeding power to airport
The Electric Power Constructors, INC crew was here on island for nearly 6 weeks over July and August. They installed new conduit in which to
Community Farm: Open House UPDATED!
Click to Download Flyer We want to hear from you about: What fresh produce you would buy locally. Your input on the draft farm and
Community Open House: Help Shape the Vision for the Saint Paul Community Farm
Click to Download Flyer We want to hear from you about: What fresh produce you would buy locally. Your input on the draft farm and
Project crew arrives on island to begin the Airport Distribution Feeder Replacement Project
June 24, 2025 – After a delayed start due to increased material costs and extremely long lead times in getting materials procured and shipped to
City Receives Additional Transportation Safety Action Plan Funding
The City of Saint Paul was recently awarded a Supplemental Planning Grant award from the US Department of Transportation’s Safe Streets and Roads For All
Aalax Landfil Project Update
Earth moving work for the new Aalax Landfill will resume in summer. The City’s new refuse truck and hooklift truck arrived on the barge in
Heavy Equipment & Materials for Landfill Delivered
Most heavy equipment and materials for the Aalax Landfill has arrived on island. Heavy equipment includes: water trailer, aluminum flatbed, loader, excavator, refuse truck and
Public Meeting: Draft of Transportation Safety Action Plan
Join us for a public meeting to review and provide feedback on the draft Transportation Safety Action Plan. Monday March 316:00-8:00 pmSaint Paul Island Rec
Public Meeting Rescheduled for February: Draft of Transportation Safety Action Plan
Join us for a public meeting to review and provide feedback on the draft Transportation Safety Action Plan. Prepared by Kuna Engineering using the information